The Cabin

The Cabin

Saturday, July 19, 2014

A New House – Episode 9 – I Second That! (Storey that is)

We are quickly approaching THE BIG DAY, THE BIG KAHUNA, That life episode of episodes (i.e., son Ben getting married this week!), so the house project is winding down temporarily.

But in the last two weeks we have layed down the 2nd floor joists and subfloor, started building 2nd floor walls and family room gable ends and chimney chase, and finished fine grading around the house.

P1010410

The floor joists supporting the 2nd floor span a full 25’ across the house, so they were a little beefier and wider (14” vs 12”) than the 1st floor that had a bearing wall to help with support. While heavyish, we managed a way to get them up there and trimmed in place – learning trick from the first floor.

 P1010411

I really like these i-joists – light and straight. But don’t assume the factory ends are square (lesson learned)

 P1010412

This an “LVL” beam (laminated veneer lumber) that is needed to create the stairwell opening.

 P1010413

Me. In the house. 

P1010416

 P1010417

i built a makeshift “boom” for the tractor to help tilt up the 18’ chimney chase. Worked great!  It would helped with those gable ends for the family room.

 P1010420

Deb has become a master with the sheathing nailer. And (unlike me) doesn’t mind the high ladder work.

 P1010421

Deb work for days finishing the grading around the house. She did a superb job.

 P1010423

The outside part of the chase is done, but we still have inside work to do.

 P1010424

We’ve started walls on the 2nd floor. Those taller walls are the shed dormers. The other side will look the same.

Sunday, July 6, 2014

A New House – Episode 8 – More Walls

 

It has been a while since i last posted our progress. Been rather busy framing walls, grading, and constructing a mini foundation….

P1010371

Walls continue to go up.  We’re doing 9’ walls in the main floor.

P1010373

got to have lots of bracing to hold things up!

 P1010375

Deb has been the tractor queen this week, doing a great job backfilling and grading around the house P1010377  .. and nailing

P1010379

 P1010378

P1010380

 P1010382  P1010386

Exterior walls are framed except the right end which we’ll leave open for now so we can bring lumber and plywood for the second floor.

 P1010384

Since the “wall incident” now all walls are framed in smaller sections

P1010388

We have our excavation guy back to remove “mount Reed”  - a big pile of high clay dirt. He moved it to the hill and dumped it over the side.
P1010390

 P1010392

Plywood covering the window openings are cut out afterwards

  P1010399

The french drain taking water from around the house .

 P1010400

 P1010401

We’ll have a fireplace in the family room, so we had to build a short wall to support the chimney chase.

 P1010404

P1010406

Nice lake view from the family room. We’ll have a french door here with windows on each side.

 P1010409

All exterior walls are framed and sheathed (except end wall)

P1010407

now doing interior walls before starting the second floor joists.

  P1010403

Tuesday, June 24, 2014

A New House – Episode 7 - Walls

As the thunder booms over the lake, I thought it would be a good time to pause and reflect. Construction safety 101 – When tilting up a really heavy 16’w x 9’H wall with sheathing, it is always a good idea to have good bracing… otherwise, that big heavy wall might tip all the way over over and nearly crush you as you stand on the ladder beneath it while beating on it with a sledge hammer … hypothetically of course.

Aside from a teaching moment we had today, the project is going well. The floor sheathing is on and 1st floor walls are going up.

P1010365

The floor sheathing is glued and nailed down with ring-shank nails. The glue is polyurethane foam floor adhesive. Great stuff and easy to apply.

P1010367

But be careful to wear gloves, otherwise your hands might become one big mass of polyurethane that has to be “mechanically removed”. Dumbass.

  P1010368

See of the second day I am smart enough to wear gloves!

 P1010370

We successfully repaired the overturned wall and it looks just like new!

The remaining walls will be built without sheathing to reduce weight and simplify and safety-ize the tilting process. The down side is that we’ll have to climb ladders to apply the 4x9 sheets of OSB. Which I hate.

Wednesday, June 18, 2014

A New House – Episode 6 – Gads, Mugsy … I’ve Been Framed!

We had a great visit with Jason and Xin Xin last weekend and took some time off to relax and have some fun fishing, golf, flying the RC planes, and BBQing. We also played some great board games.

P1010329

Jason teaching Xin Xin the basics

 P1010336

Xin Xin mostly played with the cat, but also took time to play with Tucker.

P1010344

Jason caught two nice trout on the lake and we decided to smoke them  to take home.

  P1010353

Flying the RC planes was a blast and we never lost a plane! (crashed a few time though). Dogfight!

When they left, we dove right in to start framing. P1010327

This is our first foray into using engineered lumber to build the house. Engineered lumber is something made by a machine as opposed to just milled like 2x6’s etc. Typically engineered lumber is made from oriented strand board (OSB) or plywood material, and you can get pretty much any length as opposed to dimensional lumber where 20’ is about the maximum. Here we have i-joists (right), OSB rim joists )middle top), and LVL’s (laminated veneer lumber (left). We’re using this material mostly for the floors, but that thicker beam on the left is the ridge beam for the main part of the house (32’ long).

 P1010354

Framing a basement wall.

 P1010355

The tractor helped tilt up the heavier walls.

P1010358

The important walls in the basement are done, so the 1st floor framing can begin. See the nifty arched header going into the TV room?

 P1010361

I can’t convey how great it is to have a wife who is willing and able to lift, haul and hammer right along side me. These 26’ i-joists are part of the 1st floor. 

P1010362

Today we finished framing the 1st floor structure.  7 work days since we started framing. Tomorrow we dive into laying down the 3/4” T&G OSB subfloor, which are in 4’X8’ sheets. Then on to framing the 1st floor walls.

Thursday, June 5, 2014

A New House – Episode 5 – Don’t be a Slab … and Stop Graveling!

 

… so as I was saying … a couple days after the walls were poured, they came back and started to remove the forms. Surprisingly this took a couple of days because of the cleaning they had to do to reuse the forms.

P1010281

While they worked, we painted the outside walls with that goopy damp proofing stuff.

P1010282

When they left we installed the radon vent pipe and ordered 25 yards of pea gravel (aka “radon rock”) for the interior of the basement under the slab

 P1010284 P1010286

Moving 25 yards or pea gravel BY HAND, is a lot of work for 50 somethings.

P1010318

We also ordered 20 yards of 2” washed rock for the perimeter under and around the perforated drain pipe.   Good thing we have a tractor.

 P1010316

After cleaning out a nice area around the footings, we started by laying down a 2” layer of rock, then laid the 4” perforated pipe on top of that layer and against the footing. The pipe we used had a filter sock on it to keep sediment out of the pipe.

  P1010319

After the pipe was laid, we poured more gravel on top, about 12”. Then another piece of 3’ wide filter material on top of the rock around the perimeter, then more rock on that. After a month, the concrete will be 100% set and we can backfill the remaining amount.

 P1010321

P1010324

Today, the concrete guys came out to pour the slab. Holy cow they were good. Smooth as glass!

P1010328

Yay! now we can start on framing! The tractor really helped with the unloading of the engineered lumber* delivered today.

P1010326

* More about engineered lumber in the next episode … stay tuned.